Adequacy of an alarm system to international standards

See how the Trigger methodology and tool together adapted an overloaded alarm system to ISA 18.2 and EEMUA 191

Mining

From crushing to transport, solutions with great experience of the processes

Project Data

INITIAL SITUATION

1.950

alarms per hour

System overloaded, not allowing the operation to follow the plant situation

FINAL SITUATION

7

alarms per hour

Delivering the necessary information for the best decision making of the operation

DEADLINE

5

months of projecting

Quick setup and working together with the client using agile methodology

Context and Challenges

In redesigning her supervisor, an important mining company found her alarm systems so overloaded that they were no longer used by the operation, so important information about the plant situation was lost. In the face of this scenario, it was necessary:

  1. Review 2 alarm systems simultaneously
  2. Working together with all areas of the plant: Operation, Automation, Maintenance and Process

Solutions Used and Equipment Provided

The Trigger tool was used to benchmark with international alarm management standards, indicate the alarms that most impacted the metrics and the need to review them.

Using agile methodology, 5 sprints were made in conjunction with the client's multidisciplinary team to re-evaluate the alarms indicated by the software, draw action plans to improve the system and create an alarm management process.

Experts

Process Engineer

Filipe Werneck

Awards

No items found.

Whitepapers

No items found.
Connect with our team of experts in various areas of industry.
Finding experts

Adequacy of an alarm system to international standards

See how the Trigger methodology and tool together adapted an overloaded alarm system to ISA 18.2 and EEMUA 191

January 25, 2021

published by

Process Engineer

Filipe Werneck

INITIAL SITUATION

1.950

alarms per hour

System overloaded, not allowing the operation to follow the plant situation

FINAL SITUATION

7

alarms per hour

Delivering the necessary information for the best decision making of the operation

DEADLINE

5

months of projecting

Quick setup and working together with the client using agile methodology

In redesigning her supervisor, an important mining company found her alarm systems so overloaded that they were no longer used by the operation, so important information about the plant situation was lost. In the face of this scenario, it was necessary:

  1. Review 2 alarm systems simultaneously
  2. Working together with all areas of the plant: Operation, Automation, Maintenance and Process